1 April 2022
AURA by Aqualand's Construction Update - April 2022
Our in-house construction team have been working hard making immense progress on site regarding the following key construction milestones:
- Excavation complete
- In ground services now complete
- Slab on ground now complete
- Eastern and Western lift core jump form now erected
- Basement level five is now being formed up in preparation to pour slab over next month
Over the next quarter, the following project milestones will be achieved:
- Over the next few months our construction focus will be to progress the basement substructure from level five to level three
- Finalising the artist for our public art piece for the area in front of the residential lobby on McLaren Street
Watch our latest construction progress update.